Project Description: |
LEOMINSTER- ROADWAY RECONSTRUCTION INCLUDING SIGNALS ON SECTIONS OF HAMILTON ST/RIVER STREET/CRAWFORD STREET
Work includes full depth roadway reconstruction, furnishing and installing drainage pipes and structures, traffic signs, curbing, traffic signal installation, constructing new sidewalks, and pavement markings.
|
Location: |
|
Resident Engineer: | Lisa Spezzaferro-Pelleti |
Construction Contract Value: | $1,208,803.00 |
Construction Bid Price: | $627,625.00 |
Initial Construction Estimate: | $281,000.00 |
District: | District 3 |
Current Status: | Work on the project is complete. (as of 07/20/2005) |
|
Bridges |
|
|
|
|