Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LEOMINSTER- ROADWAY RECONSTRUCTION INCLUDING SIGNALS ON SECTIONS OF HAMILTON ST/RIVER STREET/CRAWFORD STREET
Work includes full depth roadway reconstruction, furnishing and installing drainage pipes and structures, traffic signs, curbing, traffic signal installation, constructing new sidewalks, and pavement markings.
Location:
  • City of Leominster
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Project Manager: Charles Hale Jr
    Estimated Total Contract Cost: $1,208,803.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project