Project Description:
DOUGLAS- RECLAMATION AND BOX WIDENING AND TURNING LANES, DAVIS STREET/MAIN STREET/NORTHEAST STREET INTERSECTION
The proposed project will consist of roadway construction, drainage improvements and installation of retaining walls. The roadway construction will include the widening of Davis Street at the new High School Site Drive and the Middle School driveway to allow left-turn and right-turn only lanes into the high school. New curb, sidewalks, signs and pavement markings will be installed. Drainage improvements include a new box culvert underneath Davis Street.
Location:
  • Town of Douglas
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $1,299,371.00
    Construction Bid Price: $956,701.55
    Initial Construction Estimate: $850,569.40
    District: District 3
    Current Status: The final coat has been place on the roadway 95% of this project has been completed. Items left to work on: Finish driveways and place signs (as of 08/02/2007)

    Contracts (1) Progress
    # 41207 -- Construction Contract
    Douglas - Rdway Reconstruction on a Section Rte 16 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/12/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The final coat has been place on the roadway 95% of this project has been completed. Items left to work on: Finish driveways and place signs
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/17/2001
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 08/28/2004
    Project Management
    25% Design 25% Package Received 01/15/2002
    25% Design 25% Package Comments to DE 09/27/2002
    75% Design 75% Package Received 04/15/2004
    75% Design 75% Package Comments to DE 07/21/2004
    Final Design PS&E Received 08/09/2004
    Final Design PS&E to FAPRO 08/09/2004