WORCESTER- ROADWAY RECONSTRUCTION ON A SECTION OF SOUTHBRIDGE STREET
Location:
  • City of Worcester
  • Resident Engineer: Angela Padavano
    Construction Contract Value: $1,479,693.74
    Construction Bid Price: $717,315.99
    Initial Construction Estimate: $506,711.00
    District: District 3

    Contracts (1) Progress
    # 31314 -- Construction Contract
    Roadway Reconstruction on a Section of Southbridge Street. RE-ADVERTISED Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/28/2001
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 12/09/1995
    Project Status Advertised 03/24/2001
    Project Management