Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROCKTON- BRIDGE REPLACEMENT, B-25-060 (AVA), BARTLETT STREET OVER SALISBURY BROOK
The work under this contract consists of the demolition of the existing superstructure and partial demolition of the substructure. The proposed structure is an integral abutment bridge comprised of spread prestressed concrete box beam supported on steel piles. The proposed work includes full depth roadway reconstruction in the immediate vicinity of the bridge construction along with the removal and stacking of existing granite curbs, installation of new granite curbing, reconstruction of driveway aprons and sidewalks, temporary and permanent utility relocation, and all other as shown on the construction plans. The roadway will be closed during the construction of the bridge and roadway approaches. A detour will be in place during the construction, but access to local residences shall be maintained at all times.
Location:
  • City of Brockton
  • Resident Engineer: Kenneth Belgrave
    Construction Contract Value: $1,080,522.00
    Construction Bid Price: $933,932.44
    Initial Construction Estimate: $1,069,600.00
    District: District 5

    Contracts (2) Progress
    # 59675 -- Construction Contract
    Bridge Replacement (B-25-060) (Concrete) Bartlett Street over Salisbury Brook. (ABP) Completed
    # 95255 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTD Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/21/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2007
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 06/27/2009
    Project Management
    100% Design 100% Package Received 12/05/2008
    100% Design 100% Package Comments to DE 03/13/2009
    25% Design 25% Package Comments to DE 08/02/1996
    25% Design Design Public Hearing 03/18/2008
    75% Design 75% Package Received 12/28/2007
    75% Design 75% Package Comments to DE 02/07/2008
    Final Design PS&E Received 05/27/2009
    Final Design PS&E to FAPRO 06/23/2009
    Consultant Contract Process Scope to DE 04/18/2007
    Consultant Contract Process NTP Issued 07/11/2008
    Consultant Contract Process Workhours Approved 07/07/2007