HALIFAX- RECONSTRUCTION OF ROUTE 36 (HOLMES STREET) FROM ROUTE 106 TO PEMBROKE T.L. (APPROX. 2 MILES)
The work under this contract consists of the reconstruction of Holmes Street (Route 36) from the intersection with Plymouth Street (Route 106) northerly to the Pembroke town line, a distance of approximately 2.0 miles. The work includes earth excavation, excavation by cold planer, full depth bituminous concrete pavement construction, bituminous concrete overlay, drainage system construction, bituminous concrete berm construction, granite curb installation, handicap accessible bituminous concrete sidewalk construction, cemented stone masonry retaining wall construction, bituminous concrete driveway construction, highway guard installation, pavement marking and sign installation, and landscaping.
Location:
  • Town of Halifax
  • Resident Engineer: Michael McGrath
    Construction Contract Value: $4,614,902.95
    Construction Bid Price: $3,292,516.00
    Initial Construction Estimate: $2,899,391.00
    District: District 5

    Contracts (1) Progress
    # 34519 -- Construction Contract
    Reconstruction of Route 36 (Holmes Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/06/1995
    Project Status Advertised 08/24/2002
    Project Status Advertised 12/27/2003
    Project Management
    100% Design 100% Package Received 09/28/1999
    100% Design 100% Package Comments to DE 07/19/2000
    25% Design 25% Package Received 07/24/1997
    25% Design 25% Package Comments to DE 03/19/1998
    25% Design Design Public Hearing 04/07/1998
    75% Design 75% Package Received 10/09/1998
    75% Design 75% Package Comments to DE 01/13/1999
    Final Design PS&E Received 08/02/2002
    Final Design PS&E to FAPRO 08/20/2002
    Consultant Contract Process NTP Issued 02/10/1995