BILLERICA- RECONSTRUCTION OF COOK STREET & ALEXANDER ROAD (11,200 FEET TOTAL)
The purpose of this project is to improve roadway safety for vehicles and pedestrian along Cook Street from Route 3A to the Wilmington town line (2600 meters) and Alexander Road from Cook Street to Wilmington town line (1400 meters).
Location:
  • Town of Billerica
  • Resident Engineer: Gregory Ramstine
    Construction Contract Value: $6,098,180.00
    Construction Bid Price: $5,377,246.20
    Initial Construction Estimate: $5,434,967.00
    District: District 4

    Contracts (2) Progress
    # 34453 -- Design -- Traffic Signing/Signals
    Statewide - provide traffic engineering services in connection with traffic signal improvement projects at statewide state highway locations and to provide engineering service Final
    # 52896 -- Construction Contract
    Billerica - Roadway Reconstruction and Related Wrok on a Section of Cook Street and Alexander Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/28/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/01/1995
    Project Review Committee Letter 09/18/1995
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 03/14/2000
    100% Design 100% Package Comments to DE 09/13/2000
    25% Design 25% Package Received 04/04/1997
    25% Design 25% Package Comments to DE 08/14/1997
    25% Design Design Public Hearing 03/18/1998
    75% Design 75% Package Received 03/09/1998
    75% Design 75% Package Comments to DE 09/15/1998
    Final Design PS&E to FAPRO 09/18/2006