Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BILLERICA- RECONSTRUCTION OF ALLEN ROAD, FROM ROUTE 3A TO WEBB BROOK ROAD (5,400 FEET)
The project consists of full depth roadway reconstruction, widening and resurfacing, drainage and landscaping improvements, installation of granite curbing and edging, retaining walls, and concrete sidewalks. Also included is the reconstruction and signalization of the Boston Road (Route 3A) / Allen Road intersection. Boston Road will be widened to two lanes in each direction at the intersection.
Location:
  • Town of Billerica
  • Construction Begins: Winter 2015/2016
    Resident Engineer: Jay Patel
    Construction Bid Price: $6,081,026.00
    District: District 4

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 89325 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Allen Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/29/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/01/1995
    Project Review Committee Letter 09/18/1995
    Project Status Advertised 07/11/2015
    Project Management
    100% Design 100% Package Received 06/21/2013
    100% Design 100% Package Comments to DE 11/08/2013
    25% Design 25% Package Received 06/04/1998
    25% Design 25% Package Comments to DE 08/13/1998
    25% Design Design Public Hearing 09/11/2012
    75% Design 75% Package Received 07/06/2006
    75% Design 75% Package Comments to DE 01/23/2007
    Final Design PS&E Received 07/16/2014
    Final Design PS&E Received 06/26/2015
    Final Design PS&E to FAPRO 07/08/2015
    Consultant Contract Process NTP Issued 08/07/1995