Project Description: |
BARNSTABLE- RECONSTRUCTION ON ROUTE 132 (2 LANES TO 4 LANES) FROM ROUTE 6 TO BEARSE'S WAY (2 MILES)
Work consists of adding a new lane in each direction, reconstructing 5 traffic signals, adding a landscaped median, adding shoulders, widening of the sidewalk and new storm drainage system. The project length is approximately 2 miles.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Project Manager: | Michael Papadopoulos![]() |
Estimated Total Contract Cost: | $12,749,017.66 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | Final Package to FAPRO (as of 09/06/2005 ) |
|
Bridges |
|
|
|