Project Description:
BARNSTABLE- RECONSTRUCTION ON ROUTE 132 (2 LANES TO 4 LANES) FROM ROUTE 6 TO BEARSE'S WAY (2 MILES)
Work consists of adding a new lane in each direction, reconstructing 5 traffic signals, adding a landscaped median, adding shoulders, widening of the sidewalk and new storm drainage system. The project length is approximately 2 miles.
Location:
  • Town of Barnstable
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Michael Papadopoulos
    Estimated Total Contract Cost: $12,749,017.66
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: Final Package to FAPRO (as of 09/06/2005 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status PRC Approved 10/03/1995
    Project Status PRC Submitted 06/09/1995
    Project Management
    Consultant Contract Process 25% Package Received 07/20/2000
    Consultant Contract Process 75% Package Received 01/04/2005
    Consultant Contract Process 100% Package Received 07/08/2005
    Consultant Contract Process PS&E Received 09/06/2005
    Consultant Contract Process 25% Package Comments to DE 06/26/2001
    Consultant Contract Process 75% Package Comments to DE 03/16/2005
    Consultant Contract Process 100% Package Comments to DE 08/16/2005
    Consultant Contract Process PS&E to FAPRO 09/06/2005
    Consultant Contract Process Design Public Hearing 08/14/2002