Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BARNSTABLE- RECONSTRUCTION ON ROUTE 132 (2 LANES TO 4 LANES) FROM ROUTE 6 TO BEARSE'S WAY (2 MILES)
Work consists of adding a new lane in each direction, reconstructing 5 traffic signals, adding a landscaped median, adding shoulders, widening of the sidewalk and new storm drainage system. The project length is approximately 2 miles.
Location:
  • Town of Barnstable
  • Resident Engineer: Thomas Ockerbloom
    Construction Contract Value: $12,749,017.66
    Construction Bid Price: $10,833,107.96
    Initial Construction Estimate: $11,969,260.00
    District: District 5

    Contracts (1) Progress
    # 49747 -- Construction Contract
    Barnstable - Roadway Reconstruction, Widening and Related wrork on a section of Rte 132 at Rte 6 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/19/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/09/1995
    Project Review Committee PRC Approved 10/03/1995
    Project Status Advertised 09/17/2005
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 07/08/2005
    100% Design 100% Package Comments to DE 08/16/2005
    25% Design 25% Package Received 07/20/2000
    25% Design 25% Package Comments to DE 06/26/2001
    25% Design Design Public Hearing 08/14/2002
    75% Design 75% Package Received 01/04/2005
    75% Design 75% Package Comments to DE 03/16/2005
    Final Design PS&E Received 09/06/2005
    Final Design PS&E to FAPRO 09/06/2005