Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CONCORD- BRIDGE REHABILITATION, C-19-013, MONUMENT STREET OVER CONCORD RIVER (FLINT'S BRIDGE)
The structure is located within the North Bridge/Monument Square Local Historic District and adjacent to the Minute Man National Historic Park. Bridge rehabilitation will be acheived through the utlization of a masonry arch strengthening sytem. Work includes a small amount of roadway approach work with guardrail installation. The bridge will be closed with traffic detoured around the bridge during construction.
Location:
  • Town of Concord
  • Resident Engineer: Jay Patel
    Construction Contract Value: $4,390,211.00
    Construction Bid Price: $3,795,065.00
    Initial Construction Estimate: $3,685,125.00
    District: District 4

    Contracts (1) Progress
    # 53851 -- Construction Contract
    Concord - Bridge Rehabilitation (C-19-03) (Stone Arch) Monument Street over the Concord River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/11/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/21/1995
    Project Review Committee PRC Approved 10/03/1995
    Project Review Committee Letter 11/29/1995
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 08/16/2006
    100% Design 100% Package Comments to DE 09/20/2006
    25% Design 25% Package Received 01/14/2005
    25% Design 25% Package Comments to DE 04/01/2005
    25% Design Design Public Hearing 12/13/2005
    25% Design 25% Plans Complete 05/18/2005
    75% Design 75% Package Received 05/02/2006
    75% Design 75% Package Comments to DE 06/30/2006
    Final Design PS&E Received 08/16/2007
    Final Design PS&E to FAPRO 08/27/2007
    Consultant Contract Process NTP Issued 04/26/2004