| Project Description: |
CHICOPEE- ROADWAY RECONSTRUCTION ON ROUTE 141 (GRATTAN STREET) FROM ROUTE I-391 TO MONTGOMERY STREET (1.8 MILES)
The proposed project consists of reconstructing Grattan Street, in the City of Chicopee, from Montgomery Street (Route 33) to the northbound off-ramp of Interstate-391 (approximately 2,720 meters). The work will include new pavement, new sidewalks and granite curbing, new and reconstructed traffic signals and drainage improvements.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Other |
| Project Manager: | Martin Leelman![]() |
| Estimated Total Contract Cost: | $4,459,810.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 2 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||