Project Description: |
LOWELL- BRIDGE REPLACEMENT, BR# L-15-027 AIKEN STREET OVER NORTHERN CANAL
This project will result in the reconstruction of the Aiken Street Bridge over the Northern Canal and the reconstruction of portions of Fr. Morissette Boulevard. The bridge superstructure will be replaced and minor improvements will be made to' the bridge abutments.
|
Location: |
|
Resident Engineer: | Mark Fedele |
Construction Contract Value: | $1,148,590.00 |
Construction Bid Price: | $991,446.00 |
Initial Construction Estimate: | $1,019,000.00 |
District: | District 4 |
Current Status: | This job is complete. (as of 02/25/2005) |
|