| Project Description: |
MARBLEHEAD- SALEM- SWAMPSCOTT- ROADWAY RECONSTRUCTION, VINNIN SQUARE (RTE 1A, LORING AVE, VINNIN ST, SALEM ST & SWAMPSCOTT MALL)
|
| Location: |
|
| Resident Engineer: | Anthony Neve![]() |
| Construction Contract Value: | $1,667,120.00 |
| Construction Bid Price: | $1,481,609.00 |
| Initial Construction Estimate: | $1,261,000.00 |
| District: | District 4 |
| Current Status: | This contract is complete. The Contractor has completed all outstanding punch list Items in the Town of Swampscott. (as of 02/25/2005) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||