Project Description:
MELROSE- WAKEFIELD- ROADWAY REHABILITATION & SIGNAL UPGRADE, MAIN STREET & GREEN STREET
The project will address existing and projected roadway and traffic safety and operational deficiencies along Main Street and Green Street in Melrose. The project covers the portion of Main Street between the Wakefield Town Line and Short Street. The project will also include limited sections of Green Street. In addition to roadway and sidewalk reconstruction, the project includes a complete traffic control upgrade at three intersections. The three locations include Main Street at Franklin Street and Lynn Fells Parkway, as well as the intersection of Green Street and Lynn Fells Parkway.
Location:
  • City of Melrose
  • Town of Wakefield
  • Resident Engineer: Mark Spinale
    Construction Contract Value: $3,259,399.00
    Construction Bid Price: $2,445,167.16
    Initial Construction Estimate: $2,341,752.00
    District: District 4

    Contracts (1) Progress
    # 42179 -- Construction Contract
    Melrose - Wakefield - Roadway Reconstruction on a Section of Main Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/29/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 03/05/2005
    Project Management
    25% Design 25% Package Received 11/28/2000
    25% Design 25% Package Comments to DE 05/31/2001
    25% Design 25% Plans Complete 06/30/2001
    75% Design 75% Package Received 10/03/2002
    75% Design 75% Package Received 08/27/2004
    75% Design 75% Package Comments to DE 05/27/2004
    75% Design 75% Package Rejected 05/14/2004
    75% Design 75% Plans Complete 12/08/2004
    Final Design PS&E Received 02/22/2005
    Final Design PS&E to FAPRO 03/01/2005