Project Description:
MELROSE- INTERSECTION & SIGNAL IMPROVEMENT TO LEBANON STREET, FROM LYNDE STREET TO MAIN STREET
This project involves improvements to Lebanon Street between Lynde Street and just north of Main Street. The work involves resurfacing and minor widening, new curbing, sidewalks, wheelchair ramps, signal modifications and upgrades at 5 intersection locations (Grove Street, East Foster Street, Upham Street, East Emerson Street and Main Street). Pedestrian signal phasing and crosswalk improvements will also be provided at these intersections.
Location:
  • City of Melrose
  • Resident Engineer: Harry Thompson Iii
    Construction Contract Value: $335,486.12
    Construction Bid Price: $3,837,156.45
    Initial Construction Estimate: $4,063,555.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 81430 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Lebanon and Related Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/23/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/30/1995
    Project Review Committee PRC Approved 10/03/1995
    Project Status Advertised 03/15/2014
    Project Management
    100% Design 100% Package Received 08/06/2009
    100% Design 100% Package Comments to DE 09/27/2011
    100% Design 100% Plans Approved 12/03/2012
    25% Design 25% Package Received 03/08/2002
    25% Design 25% Package Comments to DE 05/12/2005
    25% Design Design Public Hearing 12/14/2006
    75% Design 75% Package Received 12/19/2007
    75% Design 75% Package Comments to DE 05/30/2008
    Final Design PS&E Received 07/24/2013
    Final Design PS&E Received 11/19/2013
    Final Design PS&E Received 02/05/2014
    Final Design PS&E Received 03/24/2014
    Final Design PS&E to FAPRO 12/24/2013
    Final Design PS&E to FAPRO 02/12/2014