Project Description:
SHUTESBURY- RECONSTRUCTION OF LEVERETT ROAD, COOLEYVILLE ROAD & PRESCOTT ROAD
The proposed project includes the rehabilitation of approximately 2.7 miles of roadway including Leverett Road, Cooleyville Road and Prescott Road in the Town of Shutesbury.
Location:
  • Town of Shutesbury
  • Resident Engineer: Brian Bellefeuille
    Construction Contract Value: $3,494,258.00
    Construction Bid Price: $3,090,144.50
    Initial Construction Estimate: $3,597,975.00
    District: District 2
    Current Status: Road under construction (as of 03/19/2008)
    Additional Info: Daily lane restrictions/reductions during the work work. All lanes open at the end of the work day and weekends. (as of 03/19/2008)

    Contracts (1) Progress
    # 52155 -- Construction Contract
    Shutesbury - Reconstruction and related work on sections of Leverett, Cooleyville and Prescott Roads Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/19/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Additional Info
    Daily lane restrictions/reductions during the work work. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/07/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 08/24/2006
    100% Design 100% Package Comments to DE 08/28/2006
    25% Design 25% Package Received 07/30/2004
    25% Design 25% Package Comments to DE 10/05/2004
    25% Design Design Public Hearing 11/16/2004
    75% Design 75% Package Received 07/22/2005
    75% Design 75% Package Comments to DE 10/24/2005
    Final Design PS&E Received 09/08/2006
    Final Design PS&E to FAPRO 09/11/2006