Project Description:
MAYNARD- INTERSECTION (AND ROADWAY) IMPROVEMENTS, 3 LOCATIONS, ROUTE 27/CONCORD ST, ROUTE 27/ACTON ST, ACTON ST/CONCORD ST
The proposed improvements for this intersection reconstruction project consists of a fully actuated traffic signal at the intersection of Route 27 (Haynes Street) and Concord Street. The work will include full depth roadway reconstruction, granite curb installation, drainage system improvements, and handicap accessible cement concrete sidewalk construction. The southerly exit of Acton Street onto Route 27 will be closed. The width of Route 27 will be increased within the project limits with a minor roadway realignment along Haynes Street as it approaches the intersection for improved sight distance. Areas disturbed by the construction will be graded as necessary and landscaped. New pavement markings and traffic signing will be installed accordingly to guide motorists through the intersection.
Location:
  • Town of Maynard
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $1,416,997.00
    Construction Bid Price: $671,761.50
    Initial Construction Estimate: $512,473.00
    District: District 3

    Contracts (1) Progress
    # 34623 -- Construction Contract
    Traffic Safety Improvements Including Signals - Route 27 and Concord Street. RE-ADVERTISED Terminated

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/20/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/03/1995
    Project Status Advertised 09/09/2000
    Project Status Advertised 02/14/2004
    Project Management
    100% Design 100% Package Received 12/03/1999
    100% Design 100% Package Comments to DE 01/31/2000
    25% Design 25% Package Received 09/22/1997
    25% Design 25% Package Comments to DE 12/04/1998
    25% Design Design Public Hearing 07/16/1998
    75% Design 75% Package Received 06/21/1999
    75% Design 75% Package Comments to DE 09/03/1999
    Final Design PS&E Received 04/05/2000
    Final Design PS&E to FAPRO 08/30/2000
    Consultant Contract Process NTP Issued 11/15/1995