Project Description:
NATICK- WELLESLEY- INTERSECTION IMPROVEMENTS @ ROUTE 9 (WORCESTER STREET) & OAK STREET, FROM 1500' WEST OF OAK STREET TO 300' EAST OF OVERBROOK DRIVE
The project consists of improvements to the existing signalized intersections at Route 9 / Oak Street in Natick and Route 9 / Overbrook Drive in Wellesley. Work also includes interconnection, sidewalk construction, pavement resurfacing and reconstruction.
Location:
  • Town of Natick
  • Town of Wellesley
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $5,739,767.00
    Construction Bid Price: $5,396,680.25
    Initial Construction Estimate: $5,810,267.50
    District: District 3

    Contracts (3) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75586 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Route 9 (Worcester Street) at Oak Island Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/12/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Section 112
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    Public Informational Meeting
    The 25% design is underway. A Public Informational meeting was held on June 23, 2009 to present the alternatives under consideration.
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/15/1994
    Project Review Committee PRC Approved 02/07/1995
    Project Review Committee Letter 06/02/2010
    Project Status Initiated 10/19/2005
    Project Status Advertised 09/15/2012
    Project Management
    100% Design 100% Package Received 04/13/2011
    100% Design 100% Package Comments to DE 09/06/2011
    25% Design 25% Package Received 09/30/2009
    25% Design 25% Package Comments to DE 01/13/2010
    25% Design Design Public Hearing 06/23/2010
    75% Design 75% Package Received 10/01/2010
    Final Design PS&E Received 05/04/2012
    Final Design PS&E Received 08/13/2012
    Final Design PS&E to FAPRO 09/11/2012