HULL- RECONSTRUCTION OF ATLANTIC AVENUE AND RELATED WORK FROM NANTASKET AVENUE TO COHASSET TOWN LINE
This project involves the reconstruction of Atlantic Avenue from Nantasket Avenue to the Cohasset Town Line. Minor widening of the roadway is also planned. Related work includes drainage improvements and reconstruction of sidewalks.
Location:
  • Town of Hull
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $7,632,584.00
    District: District 5
    Current Status: Current Operations: GC Patching around structures and general cleanup. Future Operations : GC prepping site for mainline paving scheduled for 5/20/2024. Milling to begin and completed the week of 5/13/24. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/25/2024)
    Additional Info: , A detour is recommended to through traffic along Jerusalem Rd from 7am to 330pm. However, Atlantic Avenue remains open to traffic with one-way alternating traffic at various work locations along Atlantic Avenue. (as of 04/25/2024)

    Contracts (1) Progress
    # 116350 -- Construction Contract
    Roadway Reconstruction and Related Work on Atlantic Avenue 86% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/12/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/04/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Status Advertised 09/18/2021
    Project Management
    100% Design 100% Package Received 03/29/2019
    100% Design 100% Package Comments to DE 08/26/2019
    25% Design 25% Package Received 08/16/2010
    25% Design 25% Package Comments to DE 02/03/2013
    25% Design Design Public Hearing 04/22/2013
    75% Design 75% Package Received 12/31/2015
    75% Design 75% Package Comments to DE 05/24/2016
    Final Design PS&E Received 02/19/2021