Project Description: |
HULL- RECONSTRUCTION OF ATLANTIC AVENUE AND RELATED WORK FROM NANTASKET AVENUE TO COHASSET TOWN LINE
This project involves the reconstruction of Atlantic Avenue from Nantasket Avenue to the Cohasset Town Line. Minor widening of the roadway is also planned. Related work includes drainage improvements and reconstruction of sidewalks.
|
Location: |
|
Construction Begins: | Winter 2021/2022 |
Resident Engineer: | Trevor O'Bryan |
Construction Bid Price: | $7,632,584.00 |
District: | District 5 |
Current Status: | Current Operations: GC Patching around structures and general cleanup. Future Operations : GC prepping site for mainline paving scheduled for 5/20/2024. Milling to begin and completed the week of 5/13/24. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/25/2024) |
Additional Info: | , A detour is recommended to through traffic along Jerusalem Rd from 7am to 330pm. However, Atlantic Avenue remains open to traffic with one-way alternating traffic at various work locations along Atlantic Avenue. (as of 04/25/2024) |
|
Bridges |
|
|
|
|