Project Description: |
CHARLEMONT- SHELBURNE- BRIDGE REHABILITATION, BR# C-05-007=S-11-003 NORTH RIVER ROAD OVER NORTH RIVER
|
Location: |
|
Resident Engineer: | Thomas Tierney |
Construction Contract Value: | $1,260,851.00 |
Construction Bid Price: | $1,220,651.00 |
Initial Construction Estimate: | $930,000.00 |
District: | District 1 |
Current Status: | Bridge was opened on 11/8/04 and the work is substantially complete. (as of 11/09/2004) |
Additional Info: | (as of 09/17/2004) |
|