WESTWOOD- BRIDGE REHABILITATIONS, BR# W-31-005 ROUTE I-95 (128) NB OVER MBTA & W-31-013 NB & SB ROUTE I-95 (128) OVER MBTA
The work to be performed for this project includes the phased demolition of the existing bridge superstructures and substructure elements, and the construction of two new bridges located on Route 128 /I-95 over the MBTA Franklin Commuter Rail Line in the Town of Westwood. The project also includes approach roadway work, permanent roadway widening, temporary relocation of roadway, groundwater control, bridge excavation, temporary support of existing utilities, utility relocation, and incidental work associated with the demolition and replacement of the bridge structure. Work will include the restoration of the site upon completion of the bridge.
Location:
  • Town of Westwood
  • Resident Engineer: Edward Moschella Jr
    Construction Contract Value: $9,019,980.00
    Construction Bid Price: $7,389,534.00
    Initial Construction Estimate: $7,733,443.00
    District: District 4
    Current Status: All Contract work and punchlist activities are complete. (as of 02/14/2008)

    Contracts (1) Progress
    # 33251 -- Construction Contract
    Two Bridge Replacements W-31-05 & W-31-13 (Steel) - Interstate 95 NB & SB over the MBTA. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2003
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All Contract work and punchlist activities are complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/11/1995
    Project Status Advertised 09/21/2002
    Project Status Advertised 11/16/2002
    Project Management
    100% Design 100% Package Received 03/11/2002
    100% Design 100% Package Comments to DE 05/06/2002
    25% Design 25% Package Received 07/02/2001
    25% Design 25% Package Comments to DE 11/19/2001
    25% Design Design Public Hearing 06/19/1996
    75% Design 75% Package Received 12/03/2001
    75% Design 75% Package Comments to DE 02/07/2002
    Final Design PS&E Received 08/22/2002
    Final Design PS&E to FAPRO 09/09/2002
    Consultant Contract Process NTP Issued 05/31/2000
    Consultant Contract Process Workhours Approved 04/07/2000