Project Description: |
WESTON- BRIDGE REPLACEMENT, W-29-001, MERRIAM STREET OVER B&M RAILROAD & MBTA
This project consists of replacing the existing wooden deck bridge with a concrete beam bridge or approved equivalent. The project will also involve the reconstruction of Merriam Street on the bridge approaches, sidewalk reconstruction, curb ramps, curb, guardrail, slope stabilization, drainage, utility relocations, and other incidental items of work.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Other |
Project Manager: | Christopher I Cameron |
Estimated Total Contract Cost: | $4,114,000.00 |
Estimated Total Federal Participating Construction Cost: | $4,400,600.00 |
District: | District 6 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 02/08/2023 ) |
|