Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROCKTON - ROADWAY RECONSTRUCTION & RELATED WORK (INCLUDING SIGNALS) ON A SECTION OF WEST ELM STREET
The project consists of roadway, sidewalk, traffic signals and related improvements on West Elm Street from Warren Avenue to West Street.
Location:
  • City of Brockton
  • Resident Engineer: Christopher Sera
    Construction Contract Value: $4,247,562.88
    Construction Bid Price: $3,746,907.82
    Initial Construction Estimate: $3,885,000.00
    District: District 5

    Contracts (1) Progress
    # 85001 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of West Elm Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/18/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/1995
    Project Review Committee PRC Approved 03/08/1996
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 05/09/2014
    100% Design 100% Package Comments to DE 07/16/2014
    25% Design 25% Package Received 10/09/2009
    25% Design 25% Package Comments to DE 06/07/2012
    25% Design Design Public Hearing 11/19/2012
    75% Design 75% Package Received 04/10/2013
    75% Design 75% Package Comments to DE 01/03/2014
    Final Design PS&E Received 09/08/2014
    Final Design PS&E to FAPRO 09/17/2014