Project Description:
MONTAGUE- RECONSTRUCTION ON GREENFIELD ROAD, FROM 195' SOUTH OF SHERMAN DRIVE TO HATCHERY RD (2.0 MILES)
MONTAGUE- RECONSTRUCTION ON GREENFIELD ROAD, FROM 195' SOUTH OF SHERMAN DRIVE TO HATCHERY RD (2.0 MILES)
Location:
  • Town of Montague
  • Construction Begins: Summer 2014
    Resident Engineer: David Virgilio
    Construction Contract Value: $5,821,132.00
    Construction Bid Price: $5,278,115.80
    Initial Construction Estimate: $5,371,616.00
    District: District 2

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 81814 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Stone Masonry Retaining Wall) on a Section of Greenfield Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/17/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/07/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Status Advertised 04/26/2014
    Project Management
    100% Design 100% Package Received 11/04/2011
    100% Design 100% Package Comments to DE 02/04/2013
    25% Design 25% Package Received 08/16/1999
    25% Design 25% Package Comments to DE 11/12/1999
    25% Design Design Public Hearing 04/04/2000
    75% Design 75% Package Received 05/15/2007
    75% Design 75% Package Comments to DE 09/26/2007
    Final Design PS&E Received 01/22/2014
    Final Design PS&E to FAPRO 04/23/2014