Project Description:
MILLIS- BRIDGE REPLACEMENT, M-23-006, PLEASANT STREET OVER CHARLES RIVER
The limits of the Pleasant Street bridge replacement project are between Myrtle Street and Turner Street for a total project length of 0.13 miles. The project also includes the reconfiguration of the Pleasant Street/Dean Street/Turner Street intersection on the south approach to improve traffic operation and safety.
Location:
  • Town of Millis
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $2,774,663.00
    Construction Bid Price: $2,433,655.10
    Initial Construction Estimate: $4,006,870.00
    District: District 3

    Contracts (3) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 66563 -- Construction Contract
    Bridge Replacement (M-23-006) (Concrete) Pleasant Street over the Charles River (ABP) Completed
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/16/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/20/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Status Advertised 07/31/2010
    Project Management
    100% Design 100% Package Received 11/23/2009
    100% Design 100% Package Comments to DE 01/28/2010
    25% Design 25% Package Received 05/23/2006
    25% Design 25% Package Comments to DE 08/21/2008
    25% Design Design Public Hearing 09/30/2008
    75% Design 75% Package Received 06/17/2009
    75% Design 75% Package Comments to DE 08/17/2009
    Final Design PS&E Received 03/05/2010
    Final Design PS&E Received 04/23/2010
    Final Design PS&E to FAPRO 07/28/2010
    Consultant Contract Process Scope to DE 04/29/2005
    Consultant Contract Process NTP Issued 07/11/2008
    Consultant Contract Process Workhours Approved 06/05/2005