Project Description:
NEWTON- WATERTOWN- RECONSTRUCTION OF PLEASANT STREET & HOWARD STREET (6,280 FT. TOTAL)
Reconstruction of Pleasant Street from the Waltham city line easterly to Main Street (Route 20) at Watertown Square, a distance of approximately 8,080 feet; and Howard Street from Pleasant Street northerly to Main Street (Route 20), a distance of approximately 1,000 feet. The project will include six signalized locations at intersections of Pleasant with Stop & Shop Driveway, Commonwealth of MA driveway, Bridge Street, Rosedale Road, Myrtle Street, and at Pedestrian Crossing approximately 450 feet east of Paramont Place.
Location:
  • City of Newton
  • Town of Watertown
  • Resident Engineer: Paul Pascucci
    Construction Contract Value: $8,844,104.69
    Construction Bid Price: $7,596,267.00
    Initial Construction Estimate: $7,627,164.50
    District: District 4

    Contracts (1) Progress
    # 56954 -- Construction Contract
    Newton-Watertown - Roadway Reconstruction and Related Work on Pleasant Street and Howard Street, PF #601686 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/13/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/29/1995
    Project Review Committee PRC Approved 12/11/1995
    Project Review Committee Letter 02/14/1996
    Project Status Advertised 07/19/2008
    Project Management
    100% Design 100% Package Received 01/09/2007
    100% Design 100% Package Comments to DE 06/14/2007
    25% Design 25% Package Received 06/18/1997
    25% Design 25% Package Comments to DE 10/21/1997
    25% Design Design Public Hearing 12/08/1999
    75% Design 75% Package Received 10/15/2002
    75% Design 75% Package Comments to DE 01/21/2005
    Final Design PS&E Received 02/08/2008
    Final Design PS&E to FAPRO 04/17/2008