Project Description:
NORTH ADAMS- BRIDGE REPLACEMENT, BR# N-14-004 PROTECTION AVENUE OVER THE HOOSIC RIVER
Location:
  • City of North Adams
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Project Manager: Joseph Mombrun
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 06/10/2000 )

    Contracts (1) Progress
    # 95255 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTD Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/06/1996
    Project Status Advertised 06/10/2000
    Project Management