Project Description:
WILMINGTON- REHABILITATION, ROUTE 129 (LOWELL STREET) FROM ROUTE 38 (MAIN STREET) TO WOBURN STREET, INCLUDES BR# W-38-024
The proposed work along Route 129 includes full depth reconstruction and widening for approximately 1,600 meters in length. Handicap accessible concrete sidewalks will be constructed along with new tree plantings and bicycle accommodation within the newly paved shoulders. The intersection of Route 129/38 will be realigned with new traffic signals and the bridge over Maple Meadow Brook will be replaced.
Location:
  • Town of Wilmington
  • Resident Engineer: William Murphy
    Construction Contract Value: $4,864,455.45
    Construction Bid Price: $4,088,515.00
    Initial Construction Estimate: $3,974,745.00
    District: District 4

    Contracts (1) Progress
    # 39876 -- Construction Contract
    Wilmington - Lowell Street (Route 129) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/09/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/25/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/07/2004
    Project Status Advertised 02/12/2005
    Project Management
    100% Design 100% Package Received 03/13/2003
    100% Design 100% Package Comments to DE 01/28/2004
    100% Design 100% Plans Complete 04/13/2004
    25% Design 25% Package Received 07/01/1998
    25% Design 25% Package Comments to DE 12/17/1998
    25% Design Design Public Hearing 03/04/1999
    75% Design 75% Package Received 06/18/1999
    75% Design 75% Package Comments to DE 05/20/2002
    Final Design PS&E Received 06/01/2004
    Final Design PS&E to FAPRO 08/02/2004
    Consultant Contract Process Scope to DE 08/20/1996