Project Description: |
CHELMSFORD- LOWELL- RESURFACING AND RELATED WORK ON THE LOWELL CONNECTOR FROM ROUTE 3/I-495 TO THE GORHAM STREET INTERCHANGE
The work consists resurfacing the Lowell Connector between Route 3/I-495 to the Gorham Street interchange.
|
Location: |
|
Resident Engineer: | James Slavit |
Construction Contract Value: | $4,643,330.85 |
Construction Bid Price: | $2,920,528.42 |
Initial Construction Estimate: | $2,896,400.00 |
District: | District 4 |
Current Status: | This project is substantially complete. A small punch list remains to be completed in the spring of 2008. (as of 02/21/2008) |
|
Bridges |
|
|
|
|