Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BUCKLAND- SHELBURNE- CLEANING AND PAINTING STEEL BRIDGE, BR# B-28-022=S-11-001 ROUTE 2A (BRIDGE STREET) OVER THE DEERFIELD RIVER
Location:
  • Town of Buckland
  • Town of Shelburne
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: John Gendall
    Estimated Total Contract Cost: $577,400.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • B28022 
    • S11001 
    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project