FOXBOROUGH- ROADWAY RECONSTRUCTION IN THE CENTRAL BUSINESS DISTRICT
This project will result in the reconstruction of eight streets within or near the central business district around the Town Common including School Street, South Street, Cocasset Street, and Bird Street. Additional roadway segments include: South Street, southerly to Liberty Street; Central Street, southeasterly to Basset Street; Cocasset Street, easterly to Pleasant Street; Mechanic Street and Bird Street, northeasterly to Railroad Avenue; and the full lengths of Liberty Street and Wall Street.
Location:
  • Town of Foxborough
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $3,083,563.52
    Construction Bid Price: $2,687,209.25
    Initial Construction Estimate: $2,489,000.00
    District: District 5

    Contracts (1) Progress
    # 33157 -- Construction Contract
    Roadway Reconstruction in the Central Business District. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/07/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/31/2002