Project Description:
WEST BROOKFIELD- BRIDGE REPLACEMENT, W-19-006, LONG HILL ROAD OVER CSX RR
The purpose of this project is to replace the Long Hill Road Bridge over the CSX Railroad on the same alignment with an increased vertical clearance over the railroad. The existing bridge deck and granite abutments will be removed and replaced with new concrete abutments and a new prefabricated concrete deck. The limit of roadway work is restricted to the area between the intersections of Long Hill Road with Front Street to the north and Freight House Road to the south. A temporary at-grade intersection across the railroad tracks will be utilized during construction.
Location:
  • Town of West Brookfield
  • Resident Engineer: Stefan Toth
    Construction Contract Value: $3,940,250.00
    Construction Bid Price: $3,399,888.00
    Initial Construction Estimate: $2,628,223.00
    District: District 2

    Contracts (4) Progress
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 58596 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58998 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 67314 -- Construction Contract
    Bridge Replacement (W-19-006) (Concrete) – Long Hill Road over the CSX Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/06/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/01/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 02/12/2010
    100% Design 100% Package Comments to DE 03/23/2010
    25% Design 25% Package Received 02/26/2008
    25% Design 25% Package Comments to DE 01/23/2009
    25% Design Design Public Hearing 03/19/2009
    75% Design 75% Package Received 08/10/2009
    75% Design 75% Package Comments to DE 08/27/2009
    Final Design PS&E Received 06/18/2010
    Final Design PS&E to FAPRO 08/09/2010
    Consultant Contract Process Scope to DE 08/14/2007
    Consultant Contract Process NTP Issued 07/11/2008