NORTH ADAMS- BRIDGE REHABILITATION, N-14-018 (HADLEY OVERPASS) ROUTE 8 (STATE STREET) OVER B&M RR AND HOOSIC RIVER
The purpose of this project is to rehabilitate the existing Hadley Overpass which carries Route 8 (State Street) over the Hoosic River and the B&M Railroad in North Adams. The bridge will remain open during staged construction.
Location:
  • City of North Adams
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $24,882,622.97
    Construction Bid Price: $24,382,860.00
    Initial Construction Estimate: $22,286,246.75
    District: District 1

    Contracts (2) Progress
    # 55674 -- Construction Contract
    North Adams - Bridge Rehabilitation (N-14-18) Route 8 over B & M Railroad and Hoosic River Completed
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/03/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/05/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 05/17/2008
    Project Management
    100% Design 100% Package Received 09/07/2007
    100% Design 100% Package Comments to DE 11/19/2007
    25% Design 25% Package Received 07/06/2006
    25% Design 25% Package Comments to DE 01/16/2007
    25% Design Design Public Hearing 03/28/2007
    75% Design 75% Package Received 05/07/2007
    75% Design 75% Package Comments to DE 07/06/2007
    Final Design PS&E Received 03/28/2008
    Final Design PS&E to FAPRO 05/09/2008
    Consultant Contract Process Scope to DE 05/23/1997
    Consultant Contract Process NTP Issued 08/14/2000