Project Description:
SOUTHAMPTON- ROAD RECONSTRUCTION, GLENDALE ROAD FROM POMEROY MEADOW ROAD TO EASTHAMPTON T.L. (1.7 MI)
This project consists of improvements to Glendale Road from Pomeroy Meadow Road to the bridge over the North Branch of the Manhan River at the Easthampton town line. Proposed work items include: full depth roadway reconstruction and widening; horizontal and vertical alignment improvements; installation of a closed drainage system to address roadway drainage problems; guardrail; and other associated work.
Location:
  • Town of Southampton
  • Resident Engineer: Michael Los
    Construction Contract Value: $2,469,745.15
    Construction Bid Price: $2,149,678.15
    Initial Construction Estimate: $2,094,458.00
    District: District 2
    Current Status: Road under construction (as of 03/21/2006)
    Additional Info: Work suspended until Spring. When work resumes, daily lane restrictions/reductions during the work week. Short temporary/daily detours also as needed. All lanes open to traffic at the end of the work day and weekends. (as of 11/27/2006)

    Contracts (1) Progress
    # 42826 -- Construction Contract
    Southampton - Glendale Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/24/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Additional Info
    Work suspended until Spring. When work resumes, daily lane restrictions/reductions during the work week. Short temporary/daily detours also as needed. All lanes open to traffic at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/05/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 05/21/2005
    Project Management
    100% Design 100% Package Received 04/14/2004
    100% Design 100% Package Comments to DE 08/08/2004
    25% Design 25% Package Received 06/01/1999
    25% Design 25% Package Comments to DE 08/01/1999
    25% Design Design Public Hearing 10/20/1999
    75% Design 75% Package Received 05/16/2000
    75% Design 75% Plans Complete 06/26/2000
    Final Design PS&E Received 05/13/2005
    Final Design PS&E to FAPRO 05/13/2005