WORCESTER- RECONSTRUCTION OF BLACKSTONE RIVER ROAD (FORMERLY MILLBURY STREET) FROM MCKEON ROAD TO LENORA STREET
The project includes full depth reconstruction, milling and resufacing with new sidewalks for a distance of 0.6 miles. Also included is a new signal at the Millbury Street/Greenwood Street intersection.
Location:
  • City of Worcester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Municipality
    Project Manager: Luciano Rabito
    Estimated Total Contract Cost: $2,247,319.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project