Project Description:
WEST SPRINGFIELD- SIGNAL UPGRADING, 2 LOCATIONS, WESTFIELD ST. AT SECOND STREET AND WESTFIELD ST. AT CHESTNUT ST.
This project will improve safety by shifting 60m (200') of Second St. 30m (100') east to realign with Chestnut St. Proposed along with this geometric improvement are traffic signal installation, new sidewalks and wheelchair ramps, granite curbing installation, minor grading and drainage improvements, and landscaping details.
Location:
  • Town of West Springfield
  • Resident Engineer: Joseph Borowiec
    Construction Contract Value: $390,803.00
    Construction Bid Price: $342,821.60
    Initial Construction Estimate: $316,125.10
    District: District 2
    Current Status: Physical work completed (as of 11/10/2005)

    Contracts (1) Progress
    # 36546 -- Construction Contract
    Traffic Safety Improvements at Westfield Street (Route 20) and Second Street/Chestnut Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/07/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/19/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/21/2004
    Project Management
    100% Design 100% Package Received 03/03/2004
    100% Design 100% Plans Approved 05/20/2004
    25% Design 25% Package Received 01/06/2003
    25% Design Design Public Hearing 03/26/2003
    75% Design 75% Package Received 07/16/2003
    Final Design PS&E Received 07/09/2004
    Final Design PS&E Received 08/04/2004
    Final Design PS&E to FAPRO 08/04/2004