Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DANVERS- RECONSTRUCTION OF LIBERTY STREET, FROM WATER/HIGH STREET INTERSECTION TO PAULINE ROAD, INCLUDES D-03-004 & D-03-014 CULVERTS
The proposed improvements consist of pavement reclamation, minor realignment and raising the profile of Liberty Street, reconstruction of a six foot sidewalk on both sides of Liberty Street, addition of a pick-up/drop-off area at Riverside School, parking spaces and reconstructing both culverts at the Porter River.
Location:
  • Town of Danvers
  • Resident Engineer: Paul Cameron
    Construction Contract Value: $11,399,257.00
    Construction Bid Price: $7,641,959.00
    Initial Construction Estimate: $6,541,489.50
    District: District 4

    Contracts (3) Progress
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 78958 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Liberty Street Including 2 Culverts. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/02/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Status Advertised 08/03/2013
    Project Management
    100% Design 100% Package Received 09/08/2010
    100% Design 100% Package Received 11/15/2012
    100% Design 100% Package Comments to DE 06/17/2013
    25% Design 25% Package Received 03/14/2006
    25% Design 25% Package Comments to DE 07/20/2009
    25% Design Design Public Hearing 03/08/2007
    75% Design 75% Package Received 10/21/2008
    75% Design 75% Package Comments to DE 07/23/2009
    Final Design PS&E Received 07/22/2013
    Final Design PS&E to FAPRO 07/31/2013