LOWELL- BRIDGE DEMOLITION, L-15-021 & NEW BRIDGE CONSTRUCTION, L-15-095, UNIVERSITY (TEXTILE) AVENUE OVER THE MERRIMACK RIVER AND NORTHERN CANAL
The existing University Avenue Bridge will be completely demolished and replaced with a new bridge approximately 200 feet to the west. The new bridge alignment provides a greater degree of mobility and congestion mitigation by providing a straighter alignment between Merrimack Street on the south and University Avenue to the north. The existing bridge will remain in service during construction of the new bridge.
Location:
  • City of Lowell
  • Resident Engineer: Daniel Boland
    Construction Contract Value: $32,483,425.00
    Construction Bid Price: $29,365,841.00
    Initial Construction Estimate: $36,237,249.00
    District: District 4

    Contracts (6) Progress
    # 54829 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review servicesto MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64320 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 67758 -- Construction Contract
    Construction of New Bridge (L-15-095) (Steel) in Different Alignment and Related Work (Including Demolition of L-15-021) University Avenue over the Merrimack River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/13/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/01/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 05/17/2010
    100% Design 100% Package Comments to DE 07/07/2010
    25% Design 25% Package Received 03/08/2006
    25% Design 25% Package Comments to DE 07/18/2008
    25% Design Design Public Hearing 11/29/2007
    75% Design 75% Package Received 12/18/2009
    75% Design 75% Package Comments to DE 03/25/2010
    Final Design PS&E Received 08/09/2010
    Final Design PS&E to FAPRO 08/27/2010
    Consultant Contract Process NTP Issued 05/10/2000