Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SANDWICH- CONSTRUCTION OF SITE IMPROVEMENTS AT THE ROUTE 6 REST AREA (WESTBOUND) (P.V. CHANGE)
Location:
  • Town of Sandwich
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $222,771.00
    Initial Construction Estimate: $150,914.00
    District: District 5

    Contracts (1) Progress
    # 99047 -- Construction Contract
    RTE 6 WB REST AREA Terminated

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/20/1999
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 02/22/1997
    Project Status Advertised 06/14/1997
    Project Status Advertised 06/06/1998
    Project Status Advertised 08/01/1998
    Project Management