PLAINVILLE- RECONSTRUCTION, ROUTE 1A (SOUTH STREET) AND BACON STREET (ROUTE 106) INTERSECTION
The proposed project consists of the reconstruction of the intersection at South Street (Route 1A) and Bacon Street (Route 106). The proposed project increase the turning radii, replace the existing traffic signals, reconstruct and widen the roadway and provide new concrete sidewalks with ADA conforming wheelchair ramps, and granite curb. Also included are drainage improvements, traffic signing, pavement markings, landscaping and other incidental work.
Location:
  • Town of Plainville
  • Resident Engineer: Michael Giovanelli
    Construction Contract Value: $602,153.00
    Construction Bid Price: $462,230.00
    Initial Construction Estimate: $422,400.00
    District: District 5

    Contracts (1) Progress
    # 45424 -- Construction Contract
    Plainville - Intersection Reconstruction and Related work including signals at Rte 1A (South Street) and Rte 106 (Beacon Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/04/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/02/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 07/12/2005
    100% Design 100% Package Comments to DE 08/26/2005
    25% Design 25% Package Received 10/31/2001
    25% Design 25% Package Comments to DE 01/18/2002
    25% Design Design Public Hearing 04/27/2004
    75% Design 75% Package Received 01/05/2005
    75% Design 75% Package Comments to DE 04/08/2005
    Final Design PS&E Received 11/14/2005
    Final Design PS&E to FAPRO 08/26/2005