Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST BRIDGEWATER- RECONSTRUCTION, MANLEY STREET FROM ROUTE 106 (WEST CENTER ST.) TO BROCKTON T.L.
Along with the reconstruction of approximately 4,420 meters of Manley Street, drainage improvements, sidewalks, granite curbing, pavement markings, traffic signing, landscaping, and other incidental work will be provided.
Location:
  • Town of West Bridgewater
  • Resident Engineer: Robert Widden
    Construction Contract Value: $5,185,618.26
    Construction Bid Price: $3,734,697.50
    Initial Construction Estimate: $3,055,592.00
    District: District 5

    Contracts (1) Progress
    # 43978 -- Construction Contract
    WEST BRIDGEWATER - Roadway Reconstruction and Related Work on Manley Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/19/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/02/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/20/2005
    Project Management
    100% Design 100% Package Received 01/14/2004
    100% Design 100% Package Comments to DE 06/21/2004
    25% Design 25% Package Received 01/05/2000
    25% Design 25% Package Comments to DE 10/06/2000
    25% Design Design Public Hearing 10/30/2001
    75% Design 75% Package Received 10/10/2002
    75% Design 75% Package Comments to DE 01/28/2003
    Final Design PS&E Received 06/06/2005
    Final Design PS&E to FAPRO 08/10/2005