Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-053 & REHABILITATION, P-10-060, HUNGERFORD STREET OVER S.W. BRANCH OF THE HOUSATONIC RIVER
Two separate bridges approximately one-half mile apart will be replaced at their respective locations with approach roadway improvements. The Hungerford Street bridge north of Route 20 will be replaced by a 18.3-meter long precast bridge with a concrete deck slab. The Hungerford Street Bridges crossing the South West Branch of the Housatonic River will be replaced with a new 9.1-meter long precast concrete bridge with a concrete deck. Both bridges will provide two 3.7-meter travel lanes and two 1.5-meter sidewalks.
Location:
  • City of Pittsfield
  • Resident Engineer: Michael Cullett
    Construction Contract Value: $2,501,887.00
    Construction Bid Price: $2,451,967.00
    Initial Construction Estimate: $2,385,768.00
    District: District 1

    Contracts (2) Progress
    # 55843 -- Construction Contract
    Pittsfield - 2 Bridge Replacements Br. Nos P-10-053 and P-10-060 Both on Hungerford Street both over the SW Branch of the Housatonic River Completed
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/18/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/21/1996
    Project Review Committee PRC Approved 08/20/1996
    Project Review Committee Letter 09/12/1996
    Project Status Advertised 05/10/2008
    Project Management
    100% Design 100% Package Received 10/02/2006
    100% Design 100% Package Comments to DE 01/18/2007
    25% Design 25% Package Received 10/20/1997
    25% Design 25% Package Comments to DE 03/02/1998
    25% Design Design Public Hearing 03/16/1998
    75% Design 75% Package Received 07/26/2001
    Final Design PS&E Received 01/23/2008
    Final Design PS&E to FAPRO 05/06/2008
    Consultant Contract Process Scope to DE 02/04/1997
    Consultant Contract Process NTP Issued 05/19/1997