BARNSTABLE- RECLAMATION OF BEARSE'S WAY FROM ROUTE 28 NORTH TO PITCHER'S WAY (4,300 FEET)
The project proposes to reconstruct Bearse's Way and provide sidewalks and bicycle accommodations to improve roadway safety for vehicles, bicycles, and pedestrians.
Location:
  • Town of Barnstable
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Project Manager: Philip Macdonald
    Estimated Total Contract Cost: $2,109,589.36
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: Final Package to FAPRO (as of 07/23/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status PRC Approved 12/11/1996
    Project Status PRC Submitted 07/17/1996
    Project Management
    Consultant Contract Process 25% Package Received 12/10/2001
    Consultant Contract Process 75% Package Received 09/11/2003
    Consultant Contract Process 100% Package Received 05/21/2004
    Consultant Contract Process PS&E Received 07/23/2004
    Consultant Contract Process 25% Package Comments to DE 04/29/2002
    Consultant Contract Process 75% Package Comments to DE 02/04/2004
    Consultant Contract Process 100% Package Comments to DE 07/02/2004
    Consultant Contract Process PS&E to FAPRO 07/23/2004
    Consultant Contract Process Design Public Hearing 04/30/2003