Project Description:
DANVERS- BRIDGE REPLACEMENT, D-03-013, ROUTE 35 (WATER STREET) OVER WATERS RIVER
A longer 2-span bridge totaling 138 feet will replace the existing Waters Street over Waters River culvert at its present location. The new bridge opening will be 3 times larger than the existing opening to improve tidal flushing and prevent upstream tidal backups. The width of roadway will be maintained and the sidewalk replaced.
Location:
  • Town of Danvers
  • Resident Engineer: Amanda Klemm
    Construction Contract Value: $7,391,060.00
    Construction Bid Price: $6,393,400.00
    Initial Construction Estimate: $6,355,746.00
    District: District 4

    Contracts (4) Progress
    # 37070 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 56268 -- Construction Contract
    Danvers - Bridge Replacement (D-03-013) Route 35 (Water Street) over the Waters River Completed
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/08/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/09/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Review Committee Letter 01/13/1997
    Project Status Advertised 09/15/2007
    Project Status Advertised 07/05/2008
    Project Management
    100% Design 100% Package Received 02/20/2006
    100% Design 100% Package Comments to DE 05/15/2006
    25% Design Design Public Hearing 03/18/1999
    75% Design 75% Package Received 08/07/2002
    75% Design 75% Package Comments to DE 04/25/2003
    Final Design PS&E Received 08/14/2007
    Final Design PS&E to FAPRO 09/10/2007
    Consultant Contract Process Scope to DE 09/25/2004