Project Description:
WORCESTER- INTERSECTION & SIGNAL IMPROVEMENTS ON BELMONT STREET (EAST - ROUTE 9) FROM DANIELS STREET TO ALVARADO AVENUE
The project involves widening of existing lanes on Belmont Street from Daniels Street to Alvarado Avenue. Construction also includes providing left turn lanes, milling and resurfacing, box widening, sidewalk reconstruction, and median work for a distance of 0.38 miles.
Location:
  • City of Worcester
  • Resident Engineer: Eric Rudenauer
    Construction Contract Value: $5,603,581.00
    Construction Bid Price: $4,976,624.50
    Initial Construction Estimate: $5,491,967.00
    District: District 3

    Contracts (2) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 68143 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) on a Section of Belmont Street (Route 9) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Construction
    Partial lane closures. Evening paving ongoing.
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/10/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Advertised 09/11/2010
    Project Status Advertised 09/18/2010
    Project Management
    25% Design 25% Package Received 10/19/2009
    25% Design 25% Package Comments to DE 12/14/2009
    25% Design Design Public Hearing 02/23/2010
    75% Design 75% Package Received 05/12/2010
    75% Design 75% Package Comments to DE 06/03/2010
    Final Design PS&E Received 07/30/2010
    Final Design PS&E to FAPRO 09/08/2010