SHIRLEY- RESURFACING & BOX WIDENING ON TOWNSEND ROAD, FROM ROUTE 225 TO TOWNSEND T.L.
The purpose of this project is to reconstruct Townsend Road from approximately ¼ mile south of the intersection of Groton Road to the Townsend Town Line. Also included is the reconstruction of Groton Road from approximately 625 feet east and 460 feet west of the Townsend Road. Other work includeds drainage improvement, new highway guardrail, stone masonry retaining walls, pavement markings, traffic signs, and other incidental necessary works.
Location:
  • Town of Shirley
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $3,831,089.00
    Construction Bid Price: $3,083,409.09
    Initial Construction Estimate: $3,020,730.50
    District: District 3

    Contracts (1) Progress
    # 53146 -- Construction Contract
    Shirley - Roadway Reconstruction and Related Work on a section of Townsend Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/11/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    Increase in Construction Cost
    This project reached 100% design in June of 2002. Due to the length of time to reach the PS&E stage, the PS&E estimate will be significantly higher to reflect inflation and material cost increases.
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/10/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Review Committee Letter 12/27/1996
    Project Status Advertised 11/04/2006
    Project Management
    100% Design 100% Package Received 06/18/2002
    100% Design 100% Package Comments to DE 05/12/2003
    25% Design 25% Package Received 04/14/1998
    25% Design 25% Package Comments to DE 06/24/1998
    75% Design 75% Package Received 12/05/2000
    75% Design 75% Package Comments to DE 02/27/2001
    Final Design PS&E Received 01/26/2005
    Final Design PS&E to FAPRO 09/07/2006