Project Description: |
MASHPEE- SIDEWALK AND SHOULDER CONSTRUCTION ALONG ROUTE 28 (FALMOUTH ROAD) FROM FALMOUTH T.L. TO SHELL BACK WAY (2,288')
|
Location: |
|
Resident Engineer: | -- not assigned -- |
Construction Contract Value: | $1,257,113.92 |
Construction Bid Price: | $959,370.40 |
Initial Construction Estimate: | $745,000.00 |
District: | District 5 |
|