Project Description: |
MAYNARD- STOW- BRIDGE REPLACEMENT, M-10-001=S-29-008, WHITE POND ROAD OVER ASSABET RIVER
Work on this project consists of the complete removal and replacement of the White Pond Road bridge over the Assabet River. Work includes the complete removal and replacement of the bridge structure, stabilization of the river bank and construction of new approaches to the bridge.
|
Location: |
|
Resident Engineer: | Julio Fontecchio |
Construction Contract Value: | $710,977.00 |
Construction Bid Price: | $668,777.00 |
Initial Construction Estimate: | $725,000.00 |
District: | District 3 |
Current Status: | MassHighway moved this work to a new contractor. Work on this project has resumed. (as of 07/20/2007) |
|