Project Description:
HUBBARDSTON- RECONSTRUCTION OF ROUTE 62 (OLD BOSTON TURNPIKE) FROM BARRE T.L. TO THE PRINCETON T.L.
This Town owned roadway project entails reclamation, resurfacing and areas of full depth construction on Route 62 (2-lanes). The work will begin at the Hubbardston/Barre Town Line and continue 4.1 miles easterly to the Hubbardston/Princeton Town Line. The project will realign the intersection of Route 62 with Twin Hill Road to improve sight distance. Drainage improvements will be made including replacing many culverts along the roadway.
Location:
  • Town of Hubbardston
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $3,551,769.00
    Construction Bid Price: $3,225,949.70
    Initial Construction Estimate: $3,311,300.00
    District: District 3

    Contracts (1) Progress
    # 58046 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 62 (Old Boston Turnpike) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/18/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/06/1996
    Project Review Committee PRC Approved 12/11/1996
    Project Review Committee Letter 12/24/1996
    Project Status Advertised 09/20/2008
    Project Management
    100% Design 100% Package Received 08/18/2008
    25% Design 25% Package Received 03/20/2008
    25% Design 25% Package Comments to DE 04/08/2008
    25% Design Design Public Hearing 05/05/2008
    Final Design PS&E Received 09/10/2008
    Final Design PS&E to FAPRO 09/16/2008