Project Description: |
BELLINGHAM- INSTALLATION OF TRAFFIC SIGNALS AT TWO LOCATIONS ON BLACKSTONE ST: RTE 126 (SOUTH MAIN ST) & RTE 140 (MECHANIC ST)
Work in this project includes roadway widening, cold planing, and resurfacing; installation of drainage pipes and structures, granite curbing and bituminous concrete sidewalks, traffic signals, signs and pavement markings.
|
Location: |
|
Resident Engineer: | Thomas Donnelly |
Construction Contract Value: | $1,845,451.78 |
Construction Bid Price: | $1,897,200.00 |
Initial Construction Estimate: | $1,442,466.50 |
District: | District 3 |
Current Status: | performing "punch list" work (as of 02/06/2006) |
|