Project Description: |
AUBURN- RECONSTRUCTION OF RTE 12 (SOUTHBRIDGE ST) FROM DRURY SQ. TO CHURCH ST. INCLUDING WIDENING BR# A-17-012 OVER DUNN'S BROOK
The work consists of roadway reconstruction, construction of new signals, and the installation of signs, pavement markings, and landscaping on Southbridge Street (Route 12), from Church Street to Auburn Street. Also included is the rehabilitation of the Southbridge Street bridge over the Auburn Pond Outlet.
|
Location: |
|
Resident Engineer: | Gerald Abato |
Construction Contract Value: | $3,547,873.25 |
Construction Bid Price: | $2,791,598.00 |
Initial Construction Estimate: | $2,575,000.00 |
District: | District 3 |
|